Package No. |
Work
Distribution (Package Name) |
Method of Award |
Contract Form |
Contract Type |
|
1 |
Commodity Supplier |
Low-bid selection
of prequalified packages |
Single phase or
purchase order |
Fixed Price |
|
2 |
Low-Bid Contractor
with Consultant Design |
|
Phased / Task
Order |
Fixed Price for
contractor incentives optional |
|
3 |
Systems Manager |
Quality-based
selection (negotiated procurement) |
Phased |
Fixed price, cost
reimburse. or time & materials incentives optional |
|
4 |
Design-Build
Contractor with Design Consultant |
Best-value
selection (based on consideration of price and quality) |
Phased |
Usually fixed
price, cost reimburse. or time & materials incentives
optional |
|
5 |
Consultant |
|
Phased / Task
Order |
Fixed price, cost
reimburse. or time & materials incentives optional |
|
6 |
Outsourcing Agency
Activity |
Low-bid may be
based on rates |
Usually single
phase |
Fixed price or
time & materials incentives optional |
|
7 |
Outsourcing Agency
Function |
Best value or
low-bid |
Single phase |
Fixed price, cost
reimburse. or time & material contracts
Incentives
optional |